Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

skip to Main Content
  0845 899 4444      sales@makers.biz   
Applemore Leisure Centre Built Up Roofing System

Applemore Leisure Centre Built Up Roofing System

Applemore Leisure Centre Built Up Roofing System

Applemore Leisure Centre Roof Build up Refurbishment

The roof structure of the Applemore Leisure Centre covering 2,400m², had several issues identified during Makers Construction detailed survey.

The existing roof system consisted of a bituminous vapour control layer, 25mm PIR insulation, 13mm fireboard, 60mm PIR insulation, and a BUR system.

This topped with a cold applied liquid system. Despite previous upgrades, the roof only achieved a U-value of 0.36 W/m²K, which fell short of current energy efficiency standards. Further inspection revealed visible fibreglass matting through the coating, indicating that the coating had not been applied to the required thickness.

The fibreglass matt, being UV unstable, had deteriorated over time, compromising the integrity of the system. In addition, water ponding on certain areas of the roof had caused the coating to wear down quicker in these sections, further weakening the structure.

Additional challenges included the presence of ineffective mushroom vents installed in isolated areas by previous contractors. These vents were intended to help dry out the original roof build up but were not successful. Some areas of the roof had coatings applied directly over loose chippings, which caused cracking due to poor adhesion. Several upstands were found to be below the recommended 150mm height as per BS 6229:2018, creating a potential failure point for the waterproofing system.

Read how the full Roof Refurbishment was carried out and how U-Value was achieved…

Call us on 0845 899 4444 or email sales@makers.biz

Applemore Leisure Centre Roof Refurbishment