Edmund House Car Park RefurbishmentMakers were commissioned to undertake a programme of concrete sampling and testing to determine the condition of the various concrete elements and also to determine if high alumina cement (HAC) had been used in various structural elements.

Fairly extensive cracking with calcite leaching had developed to the soffit of the deck slabs to the basement and lower basement car parks.

From the concrete testing it was apparent that there were several areas of defective concrete to the tops of the deck slabs, bases of several columns adjacent to the ramps and the deck slab soffits.

See the .pdf for the full Basement Car Park Refurbishment Case Study…

Call us on 0845 899 4444 or email sales@makers.biz

Edmund House Basement Car Park Refurbishment - Case Study

Our Services

Our Services

READ MORE

Case Studies

Case Studies

READ MORE

Our Clients

Our Clients

READ MORE

What Our Clients Say

The best contractor I have ever used on a major car park refurbishment. As far as Makers are concerned there is no improvement needed!

Senior Engineer, NPS Norwich Limited St Giles MSCP, Norwich

Makers provided all works to a very high quality and were highly accommodating in dealing with additional scope of works.

Director, Building & Consultancy, CBRE Mailbox, Birmingham

Makers delivered an excellent project on time and under budget… I would not hesitate in recommending Makers.

Facilities Manager, Hertfordshire County Council County Hall, Hertford

It was a really professional delivery from start to finish of the contract… Couldn't fault it.

Simon Richardson Villa Farm
Back To Top